Microsoft Project Exported Information

Project2


Project Start Date: Wed 3/5/03
Project Finish Date: Fri 3/21/03

Tasks with Assignments

ID
Task Name
WorkDurationStartFinish% Work Complete
1
TEAM 6. Manohar Darapureddi, Joe Garfield, Jianwei Zhuang, Pedro Diaz
0 hrs0 daysWed 3/5/03Wed 3/5/030%
2
PROJECT 2.
288 hrs13 daysThu 3/6/03Fri 3/21/030%
3
Hardware.
96 hrs10 daysThu 3/6/03Tue 3/18/030%
4
Design
32 hrs2 daysThu 3/6/03Fri 3/7/030%
3
Joe G
16 hrs Thu 3/6/03Fri 3/7/030%
4
Pedro D
16 hrs Thu 3/6/03Fri 3/7/030%
5
Develop.
32 hrs2 daysSat 3/8/03Mon 3/10/030%
3
Joe G
16 hrs Sat 3/8/03Mon 3/10/030%
4
Pedro D
16 hrs Sat 3/8/03Mon 3/10/030%
6
Testing
16 hrs1 dayTue 3/11/03Tue 3/11/030%
3
Joe G
8 hrs Tue 3/11/03Tue 3/11/030%
4
Pedro D
8 hrs Tue 3/11/03Tue 3/11/030%
7
Documentation.
16 hrs2 daysMon 3/17/03Tue 3/18/030%
4
Pedro D
16 hrs Mon 3/17/03Tue 3/18/030%
8
Software.
192 hrs13 daysThu 3/6/03Fri 3/21/030%
9
Design
48 hrs3 daysThu 3/6/03Sat 3/8/030%
1
Manohar D.
24 hrs Thu 3/6/03Sat 3/8/030%
2
Jianwei Z
24 hrs Thu 3/6/03Sat 3/8/030%
10
Develop
48 hrs3 daysMon 3/10/03Wed 3/12/030%
1
Manohar D.
24 hrs Mon 3/10/03Wed 3/12/030%
2
Jianwei Z
24 hrs Mon 3/10/03Wed 3/12/030%
11
Debugging.
16 hrs1 dayThu 3/13/03Thu 3/13/030%
1
Manohar D.
8 hrs Thu 3/13/03Thu 3/13/030%
2
Jianwei Z
8 hrs Thu 3/13/03Thu 3/13/030%
12
Integration
16 hrs1 dayFri 3/14/03Fri 3/14/030%
1
Manohar D.
8 hrs Fri 3/14/03Fri 3/14/030%
2
Jianwei Z
8 hrs Fri 3/14/03Fri 3/14/030%
13
Testing
48 hrs2 daysMon 3/17/03Tue 3/18/030%
1
Manohar D.
16 hrs Mon 3/17/03Tue 3/18/030%
2
Jianwei Z
16 hrs Mon 3/17/03Tue 3/18/030%
3
Joe G
16 hrs Mon 3/17/03Tue 3/18/030%
14
Documentation
16 hrs2 daysTue 3/18/03Wed 3/19/030%
1
Manohar D.
16 hrs Tue 3/18/03Wed 3/19/030%
15
Fall Back Time.
0 hrs2 daysThu 3/20/03Fri 3/21/030%